WEEK 5 (18.MAY.2010) - PROJECT LIFE CYCLE - NETWORK DIAGRAMS

This week lesson is all about calculation on the scheduling time plan.

Activity is an element of the project that requires time, either while people working or while people waiting. It is a time from the starting of the project until the end of the project.
Critical path, is the longest path through the network. If an activity on the critical path is delayed, the entire project will be delayed.

We did a lot of exercises in class to ensure that all of us really understand on how to work on the network diagrams...finding the start and finish date of a project scheduling.

Here are the progress of our tutorial 2 (weekly update)..

  • brainstorming on the WBS...the main activity, and subtask. We have came out with 7 main activities. Each of us are responsible on each of the activity. So, we are all come out with possible acitvities...
  • we meet up to run through on the sub-task that we have think of. From here we are filtering every subtask and pick the ones that we think are the best to be put into our project assignment.
  • we are using mind-map software to adapt the above mind-mapping.